Eltham High Street and Eltham Hill to be closed nights at start of July

A quick post to let you know that Council Officers have written to me to let me know that carriageway resurfacing work is due to take place in Eltham High Street/Eltham Hill between Well Hall Road and Kingsground at the start of July.  Officer wrote as follows:

“The section of road will be resurfaced under night time closures between the Monday the 3rd July and Thursday the 13th July 2017. Work will start each evening at 8.30 pm and will finish by 5am the following morning although the noisiest activities will be restricted to before 11pm each night. Local diversions will be put in place. The road will reopen during each day. Temporary arrangements for the affected bus stop will be put in place by London Buses.”

Apparently the work forms part of the Borough’s Principal Roads Major Maintenance Programme for 2017/18 and compliments the work carried out for the Eltham High Street Public Realm Improvement work.

The letter I received is here: Eltham High Street resurfacing summer 2017